When preparing the monthly status report, the project manager finds SPI = 0.75 and CPI = 1.25. The first project status review is coming up, and the manager wants to emphasize that the project is under control. How should the manager report the project status to key stakeholders?
Choose an answer
Tap an option to check your answer.
Correct answer: Report that the project is behind schedule but that adding an experienced resource will restore the schedule while maintaining the budget.
Why this is the answer
The correct answer is to report that the project is behind schedule but that adding an experienced resource will restore the schedule while maintaining the budget. An SPI of 0.75 indicates the project is behind schedule (earning only 75% of the planned value for the work completed). A CPI of 1.25 indicates the project is under budget (earning $1.25 for every $1 spent). The project manager needs to address the schedule variance proactively. Suggesting a solution like adding a resource to restore the schedule while maintaining the budget demonstrates control and a plan for recovery, which is what stakeholders want to hear. Preparing a detailed presentation on earned value is not the most effective way to convey status to stakeholders who are primarily interested in the project's health and recovery plan. Performing a root cause analysis is a good internal step but not the primary way to report status to stakeholders in this context. Stating the project is not tracking as expected but remains under control because the next milestone is far away is misleading and doesn't address the current schedule variance or offer a solution.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed