Which of the following steps in the risk management process involves establishing the scope and potential risks involved with a project?
Choose an answer
Tap an option to check your answer.
Correct answer: Risk identification.
Why this is the answer
Risk identification is the correct answer because it is the initial phase where an organization defines the project's boundaries, objectives, and then systematically uncovers potential threats and vulnerabilities that could impact those objectives. This includes brainstorming, reviewing documentation, and consulting experts to create a comprehensive list of risks. Risk assessment involves analyzing the identified risks to determine their likelihood and impact. Risk treatment focuses on developing and implementing strategies to mitigate, transfer, avoid, or accept risks. Risk monitoring and review is an ongoing process to track identified risks, identify new risks, and evaluate the effectiveness of risk treatment plans.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed