While reviewing phase-closing documents, the customer calls saying the project is not generating any value for the company. What should the project manager do?
Choose an answer
Tap an option to check your answer.
Correct answer: Validate the project scope, objectives, and outcomes with the customer..
Why this is the answer
The project manager should validate the project scope, objectives, and outcomes with the customer because this addresses the customer's concern directly and systematically. By reviewing these foundational elements, the project manager can identify any misunderstandings, misalignments, or changes in customer expectations that might be causing the perception of no value. This proactive step allows for clarification and potential corrective actions before final closure. Waiting to close the project is not ideal as it delays formal completion and doesn't address the root cause. Analyzing activities for value generation is too late in the project lifecycle, as the project is already in phase closing. Performing a cost-benefit analysis at this stage might confirm the customer's perception but doesn't directly resolve the underlying communication or expectation gap.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed