While reviewing program risks and issues, a stakeholder asks when a particular risk might become an issue. Which artifact should the project manager provide?
Choose an answer
Tap an option to check your answer.
Correct answer: Risk register.
Why this is the answer
The Risk Register is the correct artifact because it contains details of identified risks, including their potential triggers, probability, impact, and proximity (when they might occur). This information directly addresses the stakeholder's question about when a particular risk might become an issue. The Project Management Plan is too broad; it outlines how the project will be executed, monitored, and controlled, but doesn't detail individual risks. The Issue Log tracks issues that have already occurred, not potential future risks. The Risk Management Plan describes how risks will be managed throughout the project, but doesn't list the specific details of each individual risk like the Risk Register does.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed