You are a project manager at a startup leading a key project with critical, time-sensitive delivery goals. A team member failed to deliver an assigned deliverable on time despite repeatedly assuring it would be completed. What should you do next?
Choose an answer
Tap an option to check your answer.
Correct answer: Meet with the team member and create a development plan to prevent missed deliverables in the future..
Why this is the answer
The best approach is to meet with the team member to understand the root cause of the missed deliverable and collaboratively create a development plan. This addresses the immediate issue while also fostering growth and preventing recurrence, aligning with a project manager's role in supporting team members. Holding a team meeting might be too broad and could embarrass the individual, potentially damaging team morale. Simply recording the issue and moving on doesn't address the underlying problem or prevent future occurrences. Issuing a formal warning without understanding the situation is punitive and can demotivate the team member, hindering future performance and trust.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed