You are managing a hybrid project that requires government regulator approval. During a daily standup, a team member raises an impediment that needs collaboration from an expert assigned to another project. What should the project manager do first?
Choose an answer
Tap an option to check your answer.
Correct answer: Check the expert’s availability within the organization on an as-needed basis.
Why this is the answer
The project manager should first check the expert's availability because this is the most immediate and practical step to resolve the impediment. The expert is already identified as having the necessary knowledge, so confirming their availability is the logical next action before escalating or seeking alternative solutions. Reviewing KPIs is premature; the immediate need is to address the impediment. Asking the project sponsor for a new resource is an escalation that should only occur if the identified expert is unavailable or if their project manager refuses to share them. Developing the team member's capabilities through mentoring and training is a long-term strategy for skill development, not an immediate solution for an urgent impediment.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed