You are the project manager for a software project in a matrix organization with virtual teams. A functional manager tells you there may be no resources available to test the software. What should you do next?
Choose an answer
Tap an option to check your answer.
Correct answer: Engage the functional manager to discuss details and secure the required support.
Why this is the answer
The correct answer is to engage the functional manager because this is the most direct and appropriate first step in a matrix organization when resource availability is questioned. The functional manager controls the resources, so a direct discussion is necessary to understand the issue, explore solutions, and secure the necessary support. Requesting a teleconference with the sponsor is premature; you should first attempt to resolve the issue at the functional level. Raising the requirements at a weekly project meeting without prior discussion with the functional manager is less effective and could lead to unnecessary conflict or delays. Emailing a procurement specialist is also premature and bypasses the established organizational structure for resource allocation.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed