You're assigned to an emergency project that must finish in a few weeks. The work will affect the local community and is near a school; you've engaged the school to learn their needs. How do you ensure the work proceeds smoothly?
Choose an answer
Tap an option to check your answer.
Correct answer: Coordinate with the school to schedule nonworking project hours during school start and end times.
Why this is the answer
The correct answer is to coordinate with the school to schedule nonworking project hours during school start and end times. This demonstrates proactive stakeholder engagement and risk mitigation, aligning with PMP principles. By collaborating, the project team minimizes disruption to the school's operations and ensures the safety of students, fostering a positive relationship with a key stakeholder. Delaying the work is not feasible for an emergency project. Simply notifying the school is reactive and doesn't address potential conflicts. Advising the school to close is an extreme measure that would likely be met with resistance and is not a collaborative solution.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed